COBie explained: handing over building data for operations

COBie often appears in BIM briefs as a handover requirement, sometimes without much explanation. This page sums up what it is, where it comes from and what it contains, based on public sources.

By Julian Bringold ·

Quick answer

COBie (Construction Operations Building information exchange) is a data format and process standard for handing over the information needed to operate and maintain a building: spaces, equipment, product types, systems and documents. It can be delivered as a spreadsheet, as an IFC file or in a database, and aims to let operations start sooner after handover.

The main COBie worksheets

GroupWorksheetsWhat they cover
DesignFacility, Floor, Space, Zone, Type, Component, SystemThe building, its floors and spaces, product types, installed components and the systems they belong to
BuildJob, Resource, SpareMaintenance jobs, the resources they need and spare parts
CommonContact, Document, AttributePeople and companies, related documents and additional properties

What COBie is

The US National Institute of Building Sciences (NIBS) describes COBie as both a data format and a process standard. Its purpose is to capture and deliver the data on equipment that will need maintenance, so that the people who run the building can start sooner after handover instead of collecting that data themselves.

COBie is part of the US National BIM Standard: version 4 of NBIMS-US includes a COBie Version 3 module. The exchange rests on IFC (ISO 16739), the open format for BIM data.

Where COBie comes from

COBie was developed by William East while he worked at the US Army Corps of Engineers, around 2007, according to Catenda's glossary. It has since been used well beyond the United States, in particular in the UK.

In the UK, BS 1192-4:2014 was a code of practice for fulfilling an employer's information exchange requirements using COBie. BSI lists it as published on 30 September 2014 and withdrawn on 16 September 2022.

Spreadsheet, IFC file or database

COBie is best known as a spreadsheet, with one worksheet per kind of information. The same data can also be exchanged as an IFC file or held in a database. Catenda describes COBie as an IFC model view definition (MVD): a defined subset of IFC for one exchange.

The table above lists the main worksheets as Catenda groups them. The full specification published by NIBS remains the reference for the exact list and the rules for each field.

COBie and ISO 19650

Clients who use ISO 19650 terms may ask for COBie as part of their asset information requirements. Our ISO 19650 overview explains that vocabulary, from organisational requirements down to exchange requirements.

Getting the data right before handover

Most of what COBie asks for already lives in the models: spaces, types, components, classifications and properties. If a property is missing from the model, it will be missing from the COBie file too. Checking the models during delivery is therefore the most direct way to get a usable handover.

IDS files are designed for that check: they state which properties must be present on which objects, and software can test every IFC model against them. Our page on BIM requirements and IDS explains how, and the guide on checking BIM requirements with IDS shows the steps in SeveUp App.

SeveUp App does not produce a COBie spreadsheet. It can export the objects, properties, quantities and classifications of your models as CSV or JSON tables, which you can map into your own handover template: see downloading your model data.

Frequently asked questions

What does COBie stand for?
Construction Operations Building information exchange. It covers the information needed to operate and maintain a building after handover.
Is COBie just a spreadsheet?
No. The spreadsheet is its best known form, but the same data can be exchanged as an IFC file or held in a database. Catenda describes COBie as an IFC model view definition.
Who created COBie?
William East, while he worked at the US Army Corps of Engineers, around 2007. NIBS now publishes it as part of the US National BIM Standard.
Is BS 1192-4 still current?
No. BSI lists BS 1192-4:2014 as withdrawn on 16 September 2022.
Can SeveUp App generate a COBie file?
No. SeveUp App checks with IDS that your IFC models carry the properties your requirements ask for, and exports model data as CSV or JSON tables that you can map into your own handover template.

Sources

Sources checked on October 21, 2026.